JSC “SI-EL” successfully finish the project of modernization of the bridge crane M20-7K-28.0 g/p 20t(10t+10t) heavy duty on the basis of its own thyristors system TSSU SIEL.
Scope of delivery:
- Control cabin with remote control, air conditioning and lighting cabinet,
- Cabinets:
- Main lift 1 x 75 kw
- Trolley movement 1 x 22 kW
- Crane movement 2 x 5 kW
- Sensors
- Lighting, heating and alarm equipment.
- Diagnostic and monitoring system
- Automated lubrication system for crane wheels.
- Cable products
Dismantling , installation and commissioning was carried out in the conditions of the current production within 2 weeks .